Construction Updates

July 2025

Over the past month at Casa, the Nazero team has made excellent progress on site, reaching several key milestones. The structural works are now 100% complete, including the installation of the steelwork on Lots 1 and 2.

Brickwork on the rear lots has also been completed, and the services rough-ins are now approximately 90% complete across all lots, setting the stage for internal works to commence soon.

Looking ahead, the team will continue to build momentum as the project moves into the next exciting phase. Over the coming month, we will see the roof, windows, and doors installed, which will fully enclose the buildings and allow internal fit-out works to begin.

This will include the start of internal finishes and joinery installation — bringing the interiors of the development to life.

We’re looking forward to seeing these spaces take shape and can’t wait to welcome people through to experience the finished product.

June 2025

We’re pleased to share that construction is progressing at an exceptional pace, with significant milestones reached across both the internal and external works.

External works are now well underway, with brickwork completed on 50% of the façade. This marks a key visual turning point for the project, bringing structure and form to the development as the buildings begin to take shape above ground.

Internally, the fit-out phase continues to gain momentum. Rough-in works for plumbing, electrical, and mechanical services have now been completed in approximately 75% of the lots – a strong indicator that we’re moving swiftly toward the next stage of construction.

With each passing week, the site is transforming, and the project is moving closer to becoming a finished product. The team is maintaining strong momentum, and we’re on track to meet upcoming key program targets.

We look forward to sharing more exciting progress in next month’s update – stay tuned as we edge closer to delivering something truly special!

May 2025

Exciting Progress On Site!

We’re thrilled to share that works on site are moving ahead at a fantastic pace! Momentum is building every day, especially now that external works are in full swing with brickwork well underway on Lots 1 and 2 – what a milestone!

The structural roof installations on Lots 1 and 2 are nearing completion, which means we’re just steps away from achieving a watertight status across the front lots – huge progress!

Over on Lots 3 and 4, we’ve hit another major milestone: the formwork was successfully stripped in mid-April, and the fit-out phase is officially underway. Meanwhile, fit-out works in Lots 1 and 2 are also progressing smoothly, with plumbing and mechanical services now fixed and taking shape.

It’s all coming together, and we can’t wait to share even more exciting developments in next month’s update-stay tuned!

14.02.2025

April 2025

14.02.2025

March 2025